San Diego, California

Qualcomm Technology

Obsidian

Description

The Obsidian Lab project consisted of safe-off & demolition of the existing mechanical and plumbing systems.  AMC furnished and installed Carrier package gas/electric units, Loren Cook utility set exhaust fans, fan powered HEPA filter diffusers with room side filter access, spring vibration curbs and bases for the new A/C units and exhaust fans, Ingersoll Rand air compressor, desiccant air dryer and a 120 gallon receiver tank.

Quick Facts

General Contractor: Commercial Builders, Inc.

Owner: Qualcomm

Contract Amount: $1,066,000

Year Completed: 2016

Square Footage:  5,125 GSF

Mechanical Engineer: MA Engineers

Building 203/204 Shell & T.I.

Description

Installed new HVAC rooftop units and associated ductwork, natural gas piping and condensate drainage piping serving classrooms on 10 existing schools. Scope also included electrical service to the new HVAC units and structural upgrades to accommodate the new rooftop HVAC units.

Quick Facts

General Contractor: DPR Construction

Owner: The County of San Diego and The San Diego Regional Building Authority

Contract Amount: $6,530,430.00

Year to be Completed: 2018

Square Footage: 158,000 GSF

Architect: Smith Group JJR

North Lab

Quick Facts

General Contractor: Level 10 Construction

Owner: Qualcomm Inc

Contract Amount: $1,711,000

Year Completed: 2015

Square Footage:  16,000 GSF

Mechanical Engineer: Dufoe Consulting Engineers

Description

The North Lab project at Qualcomm, in addition to safe-off and demolition of the existing A/C Units, included furnishing and installing Hunt Air custom air handlers, Bell & Gossett plate and frame water/water heat exchangers, Bell & Gossett base mounted pumps, Trane indoor air handler, variable speed drivers, CHW expansion tank and CHW air separator, humidifiers, smoke/fire dampers, VAV boxes, registers and grilles. 

Building Q Addition 

Description

Under Construction: check back soon for more information 

Quick Facts

General Contractor: CW Driver

Owner: Qualcomm

Contract Amount: $5,627,000

Year Completed: 2013

Square Footage:  248,938 GSF

Mechanical Engineer: Dufoe Consulting Engineers 

Pacific Center Campus 

Quick Facts

General Contractor: DPR Construction

Owner: Qualcomm

Contract Amount: $3,305,000

Year Completed: 201

Square Footage:   GSF

Mechanical Engineer: 

Description

Under Construction: check back soon for more information