San Diego, California
Qualcomm Technology
Obsidian
Description
The Obsidian Lab project consisted of safe-off & demolition of the existing mechanical and plumbing systems. AMC furnished and installed Carrier package gas/electric units, Loren Cook utility set exhaust fans, fan powered HEPA filter diffusers with room side filter access, spring vibration curbs and bases for the new A/C units and exhaust fans, Ingersoll Rand air compressor, desiccant air dryer and a 120 gallon receiver tank.
Quick Facts
General Contractor: Commercial Builders, Inc.
Owner: Qualcomm
Contract Amount: $1,066,000
Year Completed: 2016
Square Footage: 5,125 GSF
Mechanical Engineer: MA Engineers
Building 203/204 Shell & T.I.
Description
Installed new HVAC rooftop units and associated ductwork, natural gas piping and condensate drainage piping serving classrooms on 10 existing schools. Scope also included electrical service to the new HVAC units and structural upgrades to accommodate the new rooftop HVAC units.
Quick Facts
General Contractor: DPR Construction
Owner: The County of San Diego and The San Diego Regional Building Authority
Contract Amount: $6,530,430.00
Year to be Completed: 2018
Square Footage: 158,000 GSF
Architect: Smith Group JJR
North Lab
Quick Facts
General Contractor: Level 10 Construction
Owner: Qualcomm Inc
Contract Amount: $1,711,000
Year Completed: 2015
Square Footage: 16,000 GSF
Mechanical Engineer: Dufoe Consulting Engineers
Description
The North Lab project at Qualcomm, in addition to safe-off and demolition of the existing A/C Units, included furnishing and installing Hunt Air custom air handlers, Bell & Gossett plate and frame water/water heat exchangers, Bell & Gossett base mounted pumps, Trane indoor air handler, variable speed drivers, CHW expansion tank and CHW air separator, humidifiers, smoke/fire dampers, VAV boxes, registers and grilles.
Building Q Addition
Description
Under Construction: check back soon for more information
Quick Facts
General Contractor: CW Driver
Owner: Qualcomm
Contract Amount: $5,627,000
Year Completed: 2013
Square Footage: 248,938 GSF
Mechanical Engineer: Dufoe Consulting Engineers
Pacific Center Campus
Quick Facts
General Contractor: DPR Construction
Owner: Qualcomm
Contract Amount: $3,305,000
Year Completed: 201
Square Footage: GSF
Mechanical Engineer:
Description
Under Construction: check back soon for more information